Sometimes it is necessary to install the locking devices on a construction site before the necessary infrastructure (power connections, IT equipment or integrator system) is available.
In this case, you can temporarily use your locking devices offline in advance until the network infrastructure is ready for use. To do so, release cards that can be used by construction site workers.
Preparing the installer
Your locking devices can remain collected in the box.
- Network switch present
(preferably for all GatewayNodes and with PoE capability). Required for configuring all components in one run (TCP only). - Network cable available to connect each GatewayNode.
- If possible, all subsequent GatewayNodes are connected to a separate network.
- Final IP configuration known (obtain from end customer if necessary).
- SmartIntego components already delivered.
- Name list for the door known (obtain from end customer if necessary).
- Cards available for the transition phase (MIFARE Classic or MIFARE DESFire).
- Label the components.
- If necessary, set up the name list of the doors (see Creating, expanding and importing a name list).
- Create the system documentation (see Document system). The system documentation shows what has been installed where.
- Connect your GatewayNodes (cable segments as in the project).
- Install the SmartIntego tool (WO) (see Install SmartIntego tool).
- Create your SmartIntego project (see Createing a SmartIntego project).
- Set up your card configuration (see Card configuration setup).
- Set up the construction site whitelist (see Create, modify and delete construction site whitelist).
- Set up SmartIntego Manager (see Setting up SmartIntego Manager).
- Add multiple RS-485 Gateway Nodes (see RS-485: Add multiple GatewayNodes).
- Manually add several LockNodes (see Add multiple LockNodes (Manual)) and add additional LockNodes manually (see Add individual LockNodes).
- If necessary, import the door name list into SmartIntego Manager (see Importing a door name list into SmartIntego Manager).
- If necessary, manage your locking devices in the SmartIntego tool (WO) (see Managing locking devices in the SmartIntego tool (WO)).
- Programme your locking devices (see Programme hybrid locking devices).
- Repeat steps 10, 12, 13, 15 and 16 for each cable segment.
Installation at the customer's site
- Mount the locking devices in the object.
- Hand out the cards (if not done yet).
IMPORTANT
Discharging the batteries
Operation exclusively via the whitelist is only recommended temporarily. The locking devices do not issue battery warnings. You will not be informed about low batteries.
- Set up the infrastructure for your locking system in the property.
- Mount your GatewayNodes.
- Check the WaveNet (see Check WaveNet).
- If necessary, relocate several locking devices (see Relocate locking devices (assign to another GatewayNode)).
- After making changes, connect your SmartIntego locking system to the integrator system (see Connecting SmartIntego to the integrator system).
- Test the system.
- Delete the construction site whitelist (see Delete the construction site whitelist).
Always compare your SmartIntego locking system with the integrator system after making changes.